WEEK 3
Project name: Color Sensation Device
Date: 3/1/2021
Team members: William Chamoun*, Malik Turner, Rhandi Whitlow, Hao Wu, Yi Yu
Presenter: William Chamoun

Updated Gantt Chart


Work Breakdown Structure


Accomplishments since last status report:
-
Conducted our fourth team meeting.
-
Revised our project Gantt chart.
-
Created project breakdown structure.
-
This week we researched different forms of temperature and vibration methods.
-
Thermoelectric cooling devices.
-
Game controller vibration motors.
-
We investigated different avenues for the application.
-
We decided to further look into the use of Xcode.
-
Has augmented reality and object recognition functionality.
Obstacles encountered since last status report:
-
NA

Risks facing the project:
-
Loss of personnel.
Objectives for the next week:
-
Look more into Thermoelectric cooling devices and try to acquire one for testing.
-
Look more into Game controller vibration motors and maybe try to find one for testing.
-
Create an X code project and start testing different functionalities.
Comments: NA